cloud for logo

The first webinar in the 2024 UWEA Webinar series was held on February 20, 2024. It was devoted to some peculiarities of connecting wind projects to the electricity grid.

The complicated and imperfect grid connection procedure is currently at the heart of many expert discussions and RES industry events in Ukraine. Thus, within this webinar, the UWEA together with its member companies IKNET Energy Engineering and LCF Law Group talked about such important issues related to the WPP grid connection procedure as electrical mode calculation and the energy storage potential impact on Ukraine’s grid. Oleksandr Zhyhalyuk, Head of the Transmission System Development Department at the NPC Ukrenergo also took part in the discussion. The webinar was moderated by Andriy Konechenkov, Chairman of the UWEA Board.

In his presentation, Yuriy Podolyak, CEO of IKNET Energy Engineering, outlined the company’s experience in calculating electrical modes based on real cases. Also, he pointed out the necessary conditions for connecting a wind farm that will be crucial in the coming years. ‘‘Grid connection is one of the main challenges for further wind deployment in Ukraine. Damages to the Ukrainian integrated power system caused by russian missile attacks, Ukraine’s power system synchronization with ENTSO-E, and the development of energy storage facilities directly influence this process. At the same time, new legislative initiatives that are planned for introduction in Ukraine will positively affect the procedure. In any case, investors can rely on IKNET’s assistance in the development of wind projects in Ukraine,’’ Mr. Podolyak said.

Ivan Bondarchuk, Counsel, Head of Energy and Natural Resources Practice at LCF Law Group, UWEA Board Member: ‘‘The current grid connection procedure poses significant risks for large-scale wind power projects. The developer is currently faced with the dilemma of either investing without any guarantee and conditions for grid connection or concluding an agreement with the grid operator and hoping to have time to build a wind farm in three years. Both options are for sure, too optimistic. Therefore, the UWEA together with the national regulator, Ministry of Energy, and NPC Ukrenergo are jointly developing a booking capacity mechanism for new RES projects. The purpose of this mechanism is to offer extra time for the development of such projects and guarantee a grid connection. According to the procedure, the developer will pay a guarantee fee which will be credited to the wind farm grid connection cost or, if the investor abandons the project, the money will be used for the development of power grids by NPC Ukrenergo.”

Oleksandr Zhyhalyuk, commented on colleagues’ visions and presentations and noted plans for the development of the national electrical grids, including the increase of interconnector capacity. “The laws that regulate the current grid connection procedure are designed to make it as simple and transparent as possible, in other words, to choose the most cost-effective option,” Mr. Zhyhalyuk underlined. He also confirmed the importance of connecting combined RES-energy storage facilities, which is common practice worldwide. Therefore, this issue is one of the priorities for the TSO’s activity.

Новини UWEA

Membership and partnership

Siemens Energy Asters Hareket Stable Energy Trancom Bureau Veritas Віндкрафт Україна Nordex Group Sika EVERLEGAL VIKOS Emergy AS JSC “WEST FINANCE AND CREDIT BANK” GEO-NET KPMG Horizon Capital Ukrgasbank Eco-Optima Dentons AdviRES Ternopil Ivan Puluj National Technical University MCL UA RENERGY Kinstellar STRUCTUM LLC ODESKRANSERVICE UKEP LLC CWP Ukraine LLC Katwind Enerji ENERCON Public Union “All-Ukrainian Energy Assembly” JSC “Energy Company of Ukraine” Legiontrans State Agency on Energy Efficiency Fenix Repower Niras INIKTI SEMIKS BETON CHESM KENK Kernel energy WPD FACTOR Южне Енерджі Ukrhydroenergo TUSIB NedZero CKS OVERSIZE s.r.o.  Ukrainian Bar Association UDP Renewables GE Vernova Greenville Energy LLC “Scientific Ecological Center ‘Green Square” EnerLoop International Online Platform Arzinger Cemark та Astor VITAGRO ENERGY ACCIONA Energy National Aviation University CMS Institute of General Energy of NAS of Ukraine Huawei Altelaw&Sempra KNESS Rystad Energy ETR Renewable Power s.r.o. Acquis Law Firm EuroCape Wind Power LLC MOSTY UKRAINE 1 LLC AVELLUM S POWER  Gresa Group ENERPROF Group TAD Elementum Energy The CLEAR ENERGY Zolin LLC PRYKARPATTYA ALTERNATIVE POWER LLC FRIENDLY WINDTECHNOLOGY WIND FARM Chemlaborreaktiv LLC Vitry Khmelnychchyny КСП-ПРОЕКТ MHP Metropoliya science and technology company LLC ТОВ «Керуюча компанія «Вітряні парки України» The Institute of Renewable energy of the NAS of Ukraine Odesenergomontazh LLC Singa Energies Sayenko Kharenko DWS UN Global Compact Ukraine Notus Energy COWI ІКNЕТ ERU Güriş SPP Development Ukraine Green Power Denmark Ingenieursozietät Prof. Katzenbach GmbH Dnipro Polytechnic Gattowind UA Shamir Energy Electroservice-Yug LLC  Atlas Global Energy Navitas Renewables GREEN SYSTEM Dealex Transport Ukraine Negabarit-Service Vestas Dragon Capital VOLTAGE GROUP UTA (Urban Technology Alliance) МЦ Баухемі LCF Deutsche WindGuard The “Oсean” Plant Business in Wind Institute of International Relations LLC “Sit in Set International Co” Baker McKenzie Green Power Sweden CRANE UKRAINE DENZAI YUZHMASH New Energy Development Bureau “VINK” LLC ENERGY TRADE GROUP (ETG.UA) Naftogaz Bioenergy Chervonohrad Lyceum

Members and partners of UWEA can be national and international companies and organizations that share the statutory goals and vision of the association, and are also ready to contribute to the development of the national wind energy market on the basis of honest partnership and mutual assistance.